Planning a blasting cleanup in Massachusetts? This guide covers the rules that apply to spent coal slag, the tests that decide how it can be managed, and what MassDEP needs before the material can be reused.
Key terms
Coal slag abrasive
Coal slag is a glassy byproduct of coal-fired boilers. It is crushed and graded for use as blasting media.
Spent media
Spent media is the abrasive after blasting. It is mixed with paint, rust, coatings, and substrate debris. Its regulatory status depends on that mix, not on the unused abrasive.
Beneficial reuse
Beneficial reuse puts a waste material to productive use instead of disposing of it. In Massachusetts, MassDEP decides through a beneficial use determination (BUD). Material used under a BUD is called a secondary material.
TCLP
The Toxicity Characteristic Leaching Procedure (EPA Method 1311) measures how much of certain contaminants can leach from a sample. It is one part of deciding whether a waste is hazardous.
What’s in your spent media?
After blasting, coal slag is mixed with whatever came off the surface. That collected material needs its own evaluation. The data sheet for unused slag only describes the starting abrasive.
Coatings matter most. Lead-based paint, chromate primers, and other metal-bearing coatings can make spent media hazardous even when the abrasive itself is not. Keep track of the abrasive and the surfaces blasted. Keep wet-blasting sludge and wash water separate from dry residue.
MassDEP’s beneficial use rule
Massachusetts’ beneficial use rule is 310 CMR 19.060. The applicant must show MassDEP that the use is beneficial and poses an insignificant potential hazard to public health, safety, or the environment. Each proposal fits one of four categories:
- Commercial products (SW 39): the material goes into a product, or is used as one, that meets industry specifications and stays controlled through its life. Products applied to the land do not fit this category.
- Regulated systems (SW 40): the material is used at a facility that MassDEP already permits, approves, or orders.
- Restricted applications (SW 41): the use relies on risk management, such as engineering controls or use limits.
- Unrestricted applications (SW 42): the use does not limit exposure. These proposals get the most comprehensive risk review.
A BUD takes the material out of solid waste rules only while it is used as the BUD allows. MassDEP can also issue general BUDs for a specific use. Anyone may follow a general BUD if they meet all of its conditions.
Processing has a limit. If MassDEP finds that the processing needed for reuse is a solid waste processing activity, the solid waste facility rules apply to it. Not sure the rule applies to your project? Ask MassDEP for a determination of applicability. MassDEP issues it within 45 days of receiving the request.
Applying to MassDEP
- Who files: any individual, business, or organization that wants to beneficially use the material. The company’s responsible official must create an ePLACE account and submit the application.
- Consult first: contact the MassDEP regional office for a pre-application consultation. If you apply without one, MassDEP may require one before it finds the application complete.
- How: file online in the EEA ePLACE portal. Upload the completed SW 39–42 application form as an attachment. Typical attachments are the lab analysis, a narrative report, and best management practices for collection, transport, and use. Include the form signed and certified by a professional engineer.
- Scope: each application covers one material type, or one material plus one “other” material. Pick the regional office for a single location or community, or pick “Statewide.”
- Fees: $2,375 for SW 39 or SW 40 and $4,455 for SW 41. SW 42 is negotiated as an individual project. An amendment (SW 44) is $1,065. Review time starts once the fee is paid.
- Local notice: send a copy to the local board of health when the use is limited to a specific location. MassDEP takes comments for at least 21 days before a final decision.
- After approval: keep records and file the reports your BUD requires. To change an approved BUD, use the “Amend” link on its ePLACE record.
MassDEP solid waste staff work out of four regional offices. Find your regional office.
Hazardous waste determination
Massachusetts hazardous waste rules are in 310 CMR 30.000, the Massachusetts Hazardous Waste Regulations. Generators decide whether a waste is hazardous under 310 CMR 30.302.
Massachusetts lists wastes with polychlorinated biphenyls (PCBs) at 50 ppm or more as hazardous waste MA02 under 310 CMR 30.131. If old coatings may contain PCBs, include PCBs in the testing.
Under 310 CMR 30.302, the generator must decide whether spent media is hazardous:
- Check whether the waste is excluded from the hazardous waste rules.
- Check whether it matches a listed hazardous waste.
- Check for hazardous characteristics, including toxicity. Test the waste, or apply knowledge of the materials and processes used.
Massachusetts requires generators to keep determination records for at least 3 years.
TCLP testing and limits
Tell the lab what you blasted and what might be in the debris. Use representative samples. Agree on the sampling plan with the lab, MassDEP, and the receiving site before collecting.
A waste is hazardous for toxicity if its TCLP extract meets or exceeds any limit in 40 CFR 261.24. The metals most relevant to coating debris are:
| Contaminant | EPA waste code | Limit (mg/L) |
|---|---|---|
| Arsenic | D004 | 5.0 |
| Barium | D005 | 100.0 |
| Cadmium | D006 | 1.0 |
| Chromium | D007 | 5.0 |
| Lead | D008 | 5.0 |
| Mercury | D009 | 0.2 |
| Selenium | D010 | 1.0 |
| Silver | D011 | 5.0 |
Passing TCLP addresses toxicity for the substances tested. It does not approve reuse or rule out other reasons a waste may be hazardous.
For a BUD, MassDEP requires data from a certified laboratory and a statistically valid sampling plan consistent with EPA SW-846.
Finding a reuse destination
MassDEP decides reuse case by case. Check any destination and proposed use with MassDEP before scheduling delivery.
When you talk to MassDEP, describe the proposal using the four categories in 310 CMR 19.060. For example, will the material go into a commercial product, or into a use where people could contact it? A material that replaces a virgin manufacturing material must meet that material’s industry specifications, or let the product meet its performance specifications. Get the receiving site’s specifications and written acceptance. If reuse is not cleared, arrange disposal that fits the waste determination.
Worker protection
- Lead: removing lead-based coatings falls under OSHA’s lead in construction standard, 29 CFR 1926.62.
- Beryllium: coal slag contains trace beryllium. OSHA has identified abrasive blasting as an operation where trace amounts can still cause significant exposure. See 29 CFR 1926.1124 and OSHA’s beryllium standards page.
- Dust: control dust during collection, storage, and loading.
Massachusetts Department of Labor Standards (DLS) covers state and local government workers in Massachusetts. Federal OSHA covers private employers.
Storage and records
Keep the material contained, control dust and runoff, and label loads by job. Keep other wastes out. A BUD application must state the storage needed to keep enough inventory for market demand. Do not handle or use the material in a way that turns it back into a solid waste.
Keep job records, data sheets, lab reports, the waste determination, MassDEP approvals, and the receiving site’s acceptance together. Record what ships and where it goes. BUD reports cover the quantity used or distributed, its sources, and any required test results.
Before pickup
- Identify the abrasive, surfaces blasted, coatings, volume, moisture, and pickup location.
- Make the hazardous waste determination and complete the required tests.
- Choose a destination and get its material specifications.
- Hold the MassDEP pre-application consultation, then file or confirm the BUD for that material and use.
- Get written acceptance and arrange pickup.
Talk to ARS about your material, location, volume, and test results. We can help you work through pickup and the next steps.
Common questions
Is a passing TCLP test enough?
No. It answers a toxicity question for the substances tested. The full waste determination, MassDEP approval, and the receiving site’s specifications still apply.
Can I use the original abrasive’s data sheet?
Keep it as background, but test or otherwise characterize the collected material. Blasting adds coatings and debris that the original data sheet does not cover.
Can I use another project’s approval?
Only if it covers your material and use. A BUD can limit the material to a specific location, a specific application, or both. A general BUD covers anyone who meets all of its conditions.
Who can apply for a BUD?
Any individual, business, or organization that wants to beneficially use the material. The company’s responsible official must submit the application in ePLACE. ARS can help gather the material information.
Does a BUD expire?
Not unless it is for a one-time use or the approval sets a limit. MassDEP keeps a BUD in effect only while the use stays beneficial and poses an insignificant potential hazard.
When do we need to test again?
Repeat the determination when the waste may have changed. Ask about retesting when the abrasive, coating, substrate, or process changes, and follow any testing in the BUD.
Rules and guidance
- MassDEP: SW 39–42 & 44 Beneficial Use Determination or Modification
- MassDEP: Instructions for SW 39–42 Beneficial Use Determinations
- 310 CMR 19.060: Beneficial Use of Solid Waste
- 310 CMR 19.000: Solid Waste Facility Regulations
- MassDEP: Permit Application Timelines and Fees Schedule
- 310 CMR 30.000: Massachusetts Hazardous Waste Regulations
- 40 CFR 262.11: Hazardous waste determination
- 40 CFR 261.24: Toxicity characteristic
- EPA Method 1311: TCLP
- EPA: Defining Hazardous Waste
- OSHA 29 CFR 1926.62: Lead in construction
- OSHA 29 CFR 1926.1124: Beryllium in construction
- Massachusetts Department of Labor Standards (DLS)