Planning a blasting cleanup in Hawaii? This guide covers the rules that apply to spent coal slag, the tests that decide how it can be managed, and what DOH needs before the material can be reused.
Key terms
Coal slag abrasive
Coal slag is a glassy byproduct of coal-fired boilers. It is crushed and graded for use as blasting media.
Spent media
Spent media is the abrasive after blasting. It is mixed with paint, rust, coatings, and substrate debris. Its regulatory status depends on that mix, not on the unused abrasive.
Beneficial reuse
Beneficial reuse puts a waste material to productive use instead of disposing of it. In Hawaii, DOH reviews proposed reuse through its solid waste facility permits.
TCLP
The Toxicity Characteristic Leaching Procedure (EPA Method 1311) measures how much of certain contaminants can leach from a sample. It is one part of deciding whether a waste is hazardous.
What’s in your spent media?
After blasting, coal slag is mixed with whatever came off the surface. That collected material needs its own evaluation. The data sheet for unused slag only describes the starting abrasive.
Coatings matter most. Lead-based paint, chromate primers, and other metal-bearing coatings can make spent media hazardous even when the abrasive itself is not. Keep track of the abrasive and the surfaces blasted. Keep wet-blasting sludge and wash water separate from dry residue.
Hawaii’s solid waste permit rule
Hawaii’s solid waste rule is HAR chapter 11-58.1, Solid Waste Management Control. It has no separate beneficial use approval. DOH works through facility permits and a few exemptions:
- A facility that stores, processes, recycles, reclaims, treats, or disposes of solid waste needs a DOH permit (HAR 11-58.1-104).
- Some operations are exempt from the permit, including minor sources as determined by DOH. They must notify DOH in writing at least 30 days before starting (HAR 11-58.1-102(c) and 11-58.1-124(b)).
- A permitted processing or storage facility may accept industrial waste only with DOH’s specific approval (HAR 11-58.1-123(c)).
The rule defines solid waste to include discarded materials from industrial and commercial operations. The owner, operator, and occupant of the property where solid waste builds up must remove it to a permitted facility. A contract for removal does not shift that duty (HAR 11-58.1-106).
The rule does not apply to inert fill material. That term covers earth, soil, rock, cured asphalt, brick, and clean concrete with no other solid waste mixed in. Spent media is not on that list.
Applying to DOH
- Who files: the owner and operator of the facility that will manage the spent media. Both sign the permit application. A corporation files through an officer, the facility’s general manager, or an authorized representative.
- How: complete DOH’s application form and the attachments for the facility type. Include the filing fee.
- Timing: submit the package at least 180 days before the planned start or change, or 180 days before an existing permit expires.
- Content: the application covers a site analysis, design, an operation plan, a fire plan, and a closure plan. The operation plan names the waste type, source, and quantity, any by-products and end products, and where the waste and by-products go.
- Market evaluation: describe the end use, show that the finished product protects human health and the environment, and evaluate available markets. Include a plan to dispose of product that cannot be sold (HAR 11-58.1-122(b)(7)).
- Fees: set by HAR 11-58.1-104(i). For example, a recycling processing or storage facility pays $250. Fees are not refunded.
- After approval: a permit lasts up to five years and can be renewed. It cannot be transferred without DOH’s written approval. DOH may modify, suspend, or revoke a permit after offering a hearing.
- Exempt operations: notify DOH in writing at least 30 days before starting. Include a site plan, an operations narrative, the owner’s approval, and proof of zoning compliance.
- Liquids and sludge: waste that contains free liquids under the Paint Filter Liquids Test (EPA Method 9095B) is liquid waste. Landfill units generally may not accept bulk liquid waste. Keep wet-blasting sludge separate and ask DOH how to manage it.
DOH Solid Waste Section: (808) 586-4226.
Hazardous waste determination
Hawaii adopts the federal hazardous waste rules by reference, with state amendments, in HAR chapters 11-260.1 to 11-279.1. The rules in effect since July 7, 2025, adopt the federal text as amended July 1, 2024. For example, HAR 11-261.1-1 adopts 40 CFR Part 261.
One Hawaii change matters if hazardous spent media is stored on site. Small and large quantity generators must record each weekly inspection of central accumulation areas in a log. The log shows the date, time, inspector, observations, and any repairs. Keep it for at least three years (HAR 11-262.1-3).
Under 40 CFR 262.11, the generator must decide whether spent media is hazardous:
- Make the determination at the point of generation, before mixing or dilution. Repeat it if the waste may have changed.
- Check whether the waste is excluded from the hazardous waste rules.
- Check whether it matches a listed hazardous waste.
- Check for hazardous characteristics, including toxicity. Use knowledge of the materials and process, testing, or both. Test when knowledge alone is not enough.
Small and large quantity generators must keep records supporting the determination for at least three years after the waste was last sent for treatment, storage, or disposal.
TCLP testing and limits
Tell the lab what you blasted and what might be in the debris. Use representative samples. Agree on the sampling plan with the lab, DOH, and the receiving site before collecting.
A waste is hazardous for toxicity if its TCLP extract meets or exceeds any limit in 40 CFR 261.24. The metals most relevant to coating debris are:
| Contaminant | EPA waste code | Limit (mg/L) |
|---|---|---|
| Arsenic | D004 | 5.0 |
| Barium | D005 | 100.0 |
| Cadmium | D006 | 1.0 |
| Chromium | D007 | 5.0 |
| Lead | D008 | 5.0 |
| Mercury | D009 | 0.2 |
| Selenium | D010 | 1.0 |
| Silver | D011 | 5.0 |
Passing TCLP addresses toxicity for the substances tested. It does not approve reuse or rule out other reasons a waste may be hazardous.
For a facility permit, DOH may require sampling data and site access (HAR 11-58.1-104(c)(2)).
Finding a reuse destination
DOH reviews reuse through facility permits. Check any destination and proposed use with DOH before scheduling delivery.
Confirm the receiving site holds a DOH permit or exemption that covers spent media. When you talk to DOH, describe the end use and how the product protects health and the environment. Explain what happens to material that cannot be used. Get the receiving site’s specifications and written acceptance. If reuse is not cleared, arrange disposal that fits the waste determination.
DOH’s lead-based paint waste guidance covers debris from abatement, renovation, and demolition of buildings. It says lead-based paint waste shall not be recycled. If your job removed lead-based paint, ask DOH how that guidance applies.
Worker protection
- Lead: removing lead-based coatings falls under OSHA’s lead in construction standard, 29 CFR 1926.62.
- Beryllium: coal slag contains trace beryllium. OSHA has identified abrasive blasting as an operation where trace amounts can still cause significant exposure. See 29 CFR 1926.1124 and OSHA’s beryllium standards page.
- Dust: control dust during collection, storage, and loading.
Hawaii Occupational Safety and Health Division (HIOSH) runs Hawaii’s OSHA-approved State Plan. For most employers, its standards apply in place of federal OSHA and must be at least as effective.
Storage and records
Keep the material contained, control dust and runoff, and label loads by job. Keep other wastes out. Remove accumulated solid waste to a permitted facility before it creates a nuisance or a health or safety hazard (HAR 11-58.1-106).
Keep job records, data sheets, lab reports, the waste determination, DOH approvals, and the receiving site’s acceptance together. Record what ships and where it goes. Keep determination records for at least three years. Permitted storage and processing facilities must log what they accept, what leaves, and where it goes (HAR 11-58.1-123(g)).
Before pickup
- Identify the abrasive, surfaces blasted, coatings, volume, moisture, and pickup location.
- Make the hazardous waste determination and complete the required tests.
- Choose a destination and get its material specifications.
- Confirm the destination holds a DOH solid waste permit or exemption that covers spent media.
- Get written acceptance and arrange pickup.
Talk to ARS about your material, location, volume, and test results. We can help you work through pickup and the next steps.
Common questions
Is a passing TCLP test enough?
No. It answers a toxicity question for the substances tested. The full waste determination, DOH approval, and the receiving site’s specifications still apply.
Can I use the original abrasive’s data sheet?
Keep it as background, but test or otherwise characterize the collected material. Blasting adds coatings and debris that the original data sheet does not cover.
Does the receiving site need a DOH permit?
Yes, unless HAR 11-58.1-102(c) exempts it. A facility that stores, processes, recycles, reclaims, or treats solid waste needs a permit. An exempt operation must still notify DOH 30 days before starting.
Does hiring a hauler or ARS shift responsibility?
No. The owner, operator, and occupant of the property must remove accumulated solid waste to a permitted facility. HAR 11-58.1-106 says removal contracts do not relieve that duty. ARS can help gather the material information.
How long can spent media be stockpiled?
HAR 11-58.1 sets no fixed period. Remove accumulated solid waste to a permitted facility before it creates a nuisance or a health or safety hazard. A solid waste storage facility needs a DOH permit. If the media is hazardous, generator accumulation limits apply.
When do we need to test again?
Repeat the determination when the waste may have changed. Ask about retesting when the abrasive, coating, substrate, or process changes, and follow any conditions in the receiving facility’s DOH permit.
Rules and guidance
- Hawaii DOH: Solid Waste Permits
- HAR chapter 11-58.1: Solid Waste Management Control
- Hawaii DOH: Solid waste facility permit instructions and fees
- Hawaii DOH: Hazardous waste rules, HAR 11-260.1 to 11-279.1
- HAR chapter 11-262.1: Standards for generators of hazardous waste
- Hawaii DOH: Disposal of Lead-Based Paint Waste
- 40 CFR 262.11: Hazardous waste determination
- 40 CFR 261.24: Toxicity characteristic
- EPA Method 1311: TCLP
- EPA: Defining Hazardous Waste
- OSHA 29 CFR 1926.62: Lead in construction
- OSHA 29 CFR 1926.1124: Beryllium in construction
- Hawaii Occupational Safety and Health Division (HIOSH)