Planning a blasting cleanup in Arizona? This guide covers the rules that apply to spent coal slag, the tests that decide how it can be managed, and what ADEQ needs before the material can be reused.
Key terms
Coal slag abrasive
Coal slag is a glassy byproduct of coal-fired boilers. It is crushed and graded for use as blasting media.
Spent media
Spent media is the abrasive after blasting. It is mixed with paint, rust, coatings, and substrate debris. Its regulatory status depends on that mix, not on the unused abrasive.
Beneficial reuse
Beneficial reuse puts a waste material to productive use instead of disposing of it. Arizona handles reuse through exemptions from the definition of solid waste. On petition, ADEQ decides case by case whether to exempt a substance.
TCLP
The Toxicity Characteristic Leaching Procedure (EPA Method 1311) measures how much of certain contaminants can leach from a sample. It is one part of deciding whether a waste is hazardous.
What’s in your spent media?
After blasting, coal slag is mixed with whatever came off the surface. That collected material needs its own evaluation. The data sheet for unused slag only describes the starting abrasive.
Coatings matter most. Lead-based paint, chromate primers, and other metal-bearing coatings can make spent media hazardous even when the abrasive itself is not. Keep track of the abrasive and the surfaces blasted. Keep wet-blasting sludge and wash water separate from dry residue.
Arizona’s solid waste exemptions
Arizona’s solid waste definition and its exemptions are in A.R.S. § 49-701.01. Any person may petition the ADEQ director to exempt a substance from the definition of solid waste. The request may be statewide or for one site.
The director decides within 90 days of receiving the written request. The decision rests on a showing that the substance is unlikely to cause or substantially contribute to a threat to public health or the environment.
- Site-specific exemption: takes effect on the date of the director’s decision. ADEQ publishes notice in the Arizona Administrative Register within 30 days.
- Statewide exemption: ADEQ starts rulemaking within 30 days to add the substance to the exemption list. The exemption takes effect with the final rule.
The statute also exempts two other groups:
- Inert material. It must not be flammable, must not decompose, and must not leach above Arizona’s aquifer water quality standards. It does not include special waste, hazardous waste, glass, or metal other than reinforcement in concrete.
- Materials generated and reused on the same site. On-site reuse must be technically feasible. At least 75 percent of the material accumulated each year must be processed or reused that year. Manage stored material to control dispersion, discharges, vectors, fire hazards, and public access.
Petitioning ADEQ
- Who files: any person may petition the ADEQ director.
- How: send a written request to the director. Say whether you want a statewide or site-specific exemption.
- What to show: that the substance is unlikely to cause or substantially contribute to a threat to public health or the environment.
- Decision: the director decides within 90 days after receiving the request.
- Scope: a site-specific exemption covers the named site. A statewide exemption applies only after rulemaking adds it to the exemption list.
ADEQ Solid Waste Section: compliance assistance (602) 771-4673, permits SolidWastePermits@azdeq.gov.
Hazardous waste determination
Arizona adopts the federal hazardous waste rules by reference in the Arizona Administrative Code, Title 18, Chapter 8. R18-8-261 incorporates 40 CFR Part 261, and R18-8-262 incorporates Part 262, each with state changes.
Arizona adds generator duties in R18-8-262. Small and large quantity generators must keep a written log of storage-area inspections for three years. Generators get EPA identification numbers from ADEQ through its myDEQ portal.
Under 40 CFR 262.11, the generator must decide whether spent media is hazardous:
- Make the determination at the point of generation, before mixing or dilution. Repeat it if the waste may have changed.
- Check whether the waste is excluded from the hazardous waste rules.
- Check whether it matches a listed hazardous waste.
- Check for hazardous characteristics, including toxicity. Use knowledge of the materials and process, testing, or both. Test when knowledge alone is not enough.
Small and large quantity generators must keep records supporting the determination for at least three years after the waste was last sent for treatment, storage, or disposal.
TCLP testing and limits
Tell the lab what you blasted and what might be in the debris. Use representative samples. Agree on the sampling plan with the lab, ADEQ, and the receiving site before collecting.
A waste is hazardous for toxicity if its TCLP extract meets or exceeds any limit in 40 CFR 261.24. The metals most relevant to coating debris are:
| Contaminant | EPA waste code | Limit (mg/L) |
|---|---|---|
| Arsenic | D004 | 5.0 |
| Barium | D005 | 100.0 |
| Cadmium | D006 | 1.0 |
| Chromium | D007 | 5.0 |
| Lead | D008 | 5.0 |
| Mercury | D009 | 0.2 |
| Selenium | D010 | 1.0 |
| Silver | D011 | 5.0 |
Passing TCLP addresses toxicity for the substances tested. It does not approve reuse or rule out other reasons a waste may be hazardous.
To count as inert material under A.R.S. § 49-701, a material must not leach above Arizona’s aquifer water quality standards in a water leach test that approximates natural infiltrating water.
Finding a reuse destination
ADEQ decides exemption petitions case by case. Check any destination and proposed use with ADEQ before scheduling delivery.
When you talk to ADEQ, name the route that fits: on-site reuse, inert material, or a petition for a site-specific or statewide exemption. Get the receiving site’s specifications and written acceptance. If reuse is not cleared, arrange disposal that fits the waste determination.
Worker protection
- Lead: removing lead-based coatings falls under OSHA’s lead in construction standard, 29 CFR 1926.62.
- Beryllium: coal slag contains trace beryllium. OSHA has identified abrasive blasting as an operation where trace amounts can still cause significant exposure. See 29 CFR 1926.1124 and OSHA’s beryllium standards page.
- Dust: control dust during collection, storage, and loading.
Arizona Division of Occupational Safety and Health (ADOSH) runs Arizona’s OSHA-approved State Plan. For most employers, its standards apply in place of federal OSHA and must be at least as effective.
Storage and records
Keep the material contained, control dust and runoff, and label loads by job. Keep other wastes out. A site that stores solid waste generated there for 90 days or less is not a solid waste facility under A.R.S. § 49-701. For on-site reuse, process or reuse at least 75 percent of the accumulated material each year.
Keep job records, data sheets, lab reports, the waste determination, ADEQ decisions, and the receiving site’s acceptance together. Record what ships and where it goes. Keep determination records for at least three years.
Before pickup
- Identify the abrasive, surfaces blasted, coatings, volume, moisture, and pickup location.
- Make the hazardous waste determination and complete the required tests.
- Choose a destination and get its material specifications.
- Confirm the exemption route with ADEQ, or file a written petition for that material and use.
- Get written acceptance and arrange pickup.
Talk to ARS about your material, location, volume, and test results. We can help you work through pickup and the next steps.
Common questions
Is a passing TCLP test enough?
No. It answers a toxicity question for the substances tested. The full waste determination, ADEQ’s decision, and the receiving site’s specifications still apply.
Can I use the original abrasive’s data sheet?
Keep it as background, but test or otherwise characterize the collected material. Blasting adds coatings and debris that the original data sheet does not cover.
Who can ask ADEQ for an exemption?
Any person may petition the director under A.R.S. § 49-701.01(C). The request must be in writing.
Can I use another project’s exemption?
Only if it covers your site and material. A site-specific exemption applies to that site. A statewide exemption applies once rulemaking adds it to the exemption list.
How long can spent media stay on the job site?
A site that stores its own solid waste for 90 days or less is not a solid waste facility. Longer storage can make the site a solid waste facility.
How fast does ADEQ decide a petition?
The director decides within 90 days after receiving the written request.
Rules and guidance
- A.R.S. § 49-701.01: Definition of solid waste; exemptions
- A.R.S. § 49-701: Solid waste definitions
- ADEQ Solid Waste Section
- A.A.C. R18-8-261: Identification and listing of hazardous waste
- A.A.C. R18-8-262: Standards for generators
- 40 CFR 262.11: Hazardous waste determination
- 40 CFR 261.24: Toxicity characteristic
- EPA Method 1311: TCLP
- EPA: Defining Hazardous Waste
- OSHA 29 CFR 1926.62: Lead in construction
- OSHA 29 CFR 1926.1124: Beryllium in construction
- Arizona Division of Occupational Safety and Health (ADOSH)